Sound Transit has begun work on the D to M Street Track and Signal Project connecting Sounder trains from Tacoma Dome Station to Lakewood. For the week of Jan. 26 to Feb. 2, you can expect to see on the D-to-M Streets Track and Signal Project:
Utilities
• Qwest will be doing work on East D Street for about a month to transfer underground utilities. This will require traffic control but no closures on East D Street.
• Level 3 Communications company will be working on South C Street between South Tacoma Way and South 25th with a shoulder closure that will not affect traffic.
• Tacoma Power will work during the day on Sunday and will set up some traffic control on East 26th Street.
D-to-M Streets construction work
• Continued work on A Street between South 26th and South 25th for sewer line work. This work involves excavation of A Street and installation of sewer pipe. A Street will reopen in April prior to the temporary closure of Pacific Avenue for 11 months.
• Excavation of a temporary storm retention pond in a Sound Transit-owned lot between A Street and Pacific Avenue. Trucks carrying material will enter and exit from South 26th Street.
• Installation of temporary wood poles for upcoming temporary lighting and signals at the corners of South 24th Street and A Street, South 27th and A Street, and South 27th and Pacific Avenue.
• Continued clearing work between Delin Street and South Tacoma Way. After that work is complete, crews will begin constructing the temporary traffic bypass for a future traffic detour during the temporary closure of Pacific Avenue for 11 months.
• Traffic control will be set up on South 27th Street between Pacific Avenue and A Street for detour street improvements.