Construction Schedule & Progress
• Sidewalks: The last portions of the sidewalk on the east side of Pacific Avenue between S. 9th & S.13th Street should be poured by the end of this week.
• Curb & Gutter: The last portions of the curb & gutter on the east side of Pacific Avenue between S. 9th & S.13th should be poured by the end of this week.
• Bulb Outs: The new bulb out on the SE corner of S. 9th Street is expected to be completed by the end of this week. Currently this work impacts eastbound and westbound traffic on S. 9th Street.
• Rain Garden: Irrigation and concrete work is ongoing as we progress through each rain garden. The liners will be installed this week with the under drain pipes and drainage gravel placed shortly after.
• Planters: The planting of trees & shrubs will begin later this week.
• Vault Infill: Work on the vault infill at 1007 Pacific Avenue began a few weeks ago and is expected to be complete by the end of this month.
• Traffic Control: Traffic control and temporary pedestrian access is in place on the east side of Pacific Avenue between S. 9th and S.13th. The outside lane of northbound through traffic and the parallel parking lane is closed for construction work.
• Daffodil Parade: The 80th Annual Daffodil Parade will be taking place this Saturday, April 13th. The parade route will be on Pacific Avenue from S.11th through S.19th Street, with queuing along Pacific Avenue from S. 7th to S.11th, including side streets.
• Y Run for Kids: The YMCA will be hosting their annual Y Run for Kids this Saturday with registration beginning at 7 am and the event ending just before the Daffodil Parade. The run begins and ends in the 1500 block of Pacific Avenue at Tollefson Plaza.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment