PAC Ave April 22 Update and Coffee Talk/Mixer

The contractor is finishing tasks in Phase 1A and has started preliminary work (temporary lighting, potholing, and tree and underground storage tank removal) between S. 7th and S. 9th St. on the west side (expanded Phase 1B).  In an effort to stay on schedule, full construction will begin on the west side between S. 7th and S. 9th St. mid-late next week, weather dependent.  This will include temporary removal of all parking and the installation of revised pedestrian routes in this area.  Traffic detours that are currently in place (use of S.13th St/S.15th St. to I-705) will remain operational.

With this new work, the majority of parking in Phase 1A will open up, with the exception of the S. 11th to S. 12th St. (Starbucks) block due to planter/stair construction in that area.  For all other blocks, the contractor will reserve two parking spaces immediately adjacent to each rain garden to complete final tasks. 

Remaining tasks associated with Phase 1A include:

  • Continued work at each rain garden/landscaping
  • Miscellaneous sidewalk placement/replacement (vault infill, cobble sections, etc.)
  • Concrete planters/stairs between S. 11th and S. 12th St.
  • Installation of remaining street lights
 
A flyer update will be distributed to the S. 7th to S. 9th St. area businesses on Monday, April 22nd.
 
In addition, there will be Coffee Talk/ Evening Mixer on Thursday, April 25th from 5:00-6:00 PM at Tacoma Cabana 728 Pacific Avenue Tacoma, WA 98402 to discuss the project.