Wednesday, July 20, 2011

Water Improvements at 9th and Broadway

Tacoma Water will be replacing 36 feet of 16” CI water main that runs north-south in Broadway at the intersection of S. 9th St (See map). This work will likely affect both East bound lanes of S. 9th St. as well as the parking and sidewalk on that side also. This work will be done by Tacoma Water crews during normal business hours and is anticipated to take place in the next couple of weeks and should only impact S. 9th St. for a couple of days. Tacoma Water crews will maintain through traffic during construction using flaggers. Access to St. Helen's for cyclists will remain open.

Thursday, July 07, 2011

Businesses Remain Open During Construction

Business owners surpass the construction’s disruptions to keep their businesses open to the people of Tacoma.

Construction workers in bright, yellow helmets roam the streets of South 25th and South 27th Street. Large cranes plow and transport enormous amounts of debris from one location to the other. Bright, diamond-shaped, orange signs read ‘detour’ and ‘sidewalk closed’.

In June, Pacific Avenue closed between South 25th Street and South 27th Street for an 11-month construction, D-to-M Street Project. This project will bring streets to new grades and construct an overpass that will allow the Sounder Train to extend service to Lakewood. Detour routes are available and, in order to keep South Tacoma Way traffic moving, Sound Transit built a special bypass road.

Although the construction expects to continue through May 2011, businesses remain open. The businesses affected by the construction, such as: Freighthouse Square, Alfred’s CafĂ©, Celebrity Cake Studio, The Melting Pot, Crystal Voyage, Stanley & Seaforts, and the Tacoma Dome want the community to know that they are open for business.

Find information and detour maps online on Sound Transit’s D-M Street Project page.

Monday, June 13, 2011

Planter Basket Repairs

The City of Tacoma’s Streets and Grounds will be repairing the planter baskets that are currently hanging on Pacific Avenue and A Street. The baskets will be removed by the vendor and may remain down for a week or two before they are all repaired and returned to their proper places. The repairs will include replacing the wire hangers which have become a safety concern as they are too lightweight, are stretching and in some cases breaking.

Questions can be directed to Rob McNair-Huff, City of Tacoma Community Relations Manager, at 253-591-5054.

Thursday, June 02, 2011

D-to-M Project Moves Forward - Pacific Avenue Closure Begins Next Week

The week of June 6 marks the beginning of an 11-month closure of Pacific Avenue to bring streets to new grades and construct an overpass that will allow the Sounder Train to extend service to Lakewood. The closure will affect Pacific Avenue between South 25th Street and South 27th Street.

To minimize disruption to the community, Sound Transit is building a special bypass road to keep South Tacoma Way traffic moving, installing temporary signalization to improve traffic flow, making road improvements to new detour routes, communicating with the public about traffic impacts, and constantly working to efficiently complete the required Pacific Avenue work.

For more information on the project, detour routes, or to sign up to receive notices, please visit the D-to-M Streets Project Page.

Friday, May 13, 2011

9th Street Improvement Project


The 9th Street Improvement Project in downtown Tacoma will improve intersections for pedestrian travel at the intersections of South 9th Street at Broadway, St Helens and Market streets. Design will include all current ADA standards. Work will include new cement concrete sidewalks, concrete crossings, curb and gutter, and street reconstruction work.

The city met with the public in May to gather feedback about the scheduling, sequencing and detour routes for the improvement project. Construction is scheduled to start this July.

Project Schedule:
Advertise: May 2011
Construction Start: July 2011
Project Completion: October 2011

For more information contact: Dan Soderlind, Project Engineer at 253‐591‐5263 or dsoderli@cityoftacoma.org.