The City of Tacoma’s Streets and Grounds will be repairing the planter baskets that are currently hanging on Pacific Avenue and A Street. The baskets will be removed by the vendor and may remain down for a week or two before they are all repaired and returned to their proper places. The repairs will include replacing the wire hangers which have become a safety concern as they are too lightweight, are stretching and in some cases breaking.
Questions can be directed to Rob McNair-Huff, City of Tacoma Community Relations Manager, at 253-591-5054.
Monday, June 13, 2011
Thursday, June 02, 2011
D-to-M Project Moves Forward - Pacific Avenue Closure Begins Next Week
The week of June 6 marks the beginning of an 11-month closure of Pacific Avenue to bring streets to new grades and construct an overpass that will allow the Sounder Train to extend service to Lakewood. The closure will affect Pacific Avenue between South 25th Street and South 27th Street.
To minimize disruption to the community, Sound Transit is building a special bypass road to keep South Tacoma Way traffic moving, installing temporary signalization to improve traffic flow, making road improvements to new detour routes, communicating with the public about traffic impacts, and constantly working to efficiently complete the required Pacific Avenue work.
For more information on the project, detour routes, or to sign up to receive notices, please visit the D-to-M Streets Project Page.
To minimize disruption to the community, Sound Transit is building a special bypass road to keep South Tacoma Way traffic moving, installing temporary signalization to improve traffic flow, making road improvements to new detour routes, communicating with the public about traffic impacts, and constantly working to efficiently complete the required Pacific Avenue work.
For more information on the project, detour routes, or to sign up to receive notices, please visit the D-to-M Streets Project Page.
Subscribe to:
Posts (Atom)