Tuesday, April 16, 2013

The Pacific Avenue Streetscape April 16 Weekly Construction Update

A special public meeting was held last week at the Chamber to discuss the project's schedule and options for making up time due to unforeseen issues.  It was proposed to expand Phase 1B to include the west side of Pacific Avenue from S. 7th to S.13th Street. In preparation for this work, the contractor will begin tree removal, the installation of temporary lighting, and potholing for buried utilities within this expanded area. The contractor will contact adjacent businesses before this preliminary work begins.   

Construction Schedule & Progress

  • Sidewalks:  The pedestrian path through Phase 1A is generally complete.  Small portions of sidewalk yet to be constructed include areas receiving a cobble finish in the vicinity of bulb outs, and gray sidewalk panels immediately adjacent to the rain gardens.
  • Curb & Gutter:  The majority of the curb & gutter on the east side of Pacific Avenue between S. 9th & S.13th is complete.  Curb and gutter work at the rain gardens is expected to be complete by the end of the month.
  • Bulb Outs:  The new bulb out on the SE corner of S. 9th Street is complete and open to pedestrian traffic. The bulb out on the NE corner of S.11th St. is tentatively planned for completion this week.
  • Electrical:  Temporary lighting is being installed on the west side of Pacific Avenue between    S. 7th and S. 9th in preparation for the start of the expanded Phase 1B.
  • Rain Garden: Concrete work continues in each rain garden in preparation for the installation of the impermeable liners and the placement of treatment media, soils and plants. Work is expected to continue through the end of the month.
  • Planters:  Topsoil has been installed at several tree pit/planter locations. Select trees were planted last week from S. 9th to S.12th Street.
  • Vault Infill: Work on the vault infill at 1007 Pacific Avenue is ongoing and is expected to be complete by early April.
  • Traffic Control: The contractor has replaced a number of the water-filled traffic barriers on the east side of Pacific Avenue with orange traffic barrels. Parking meters and signs are expected to be installed within the next two weeks. Once these are in place, select areas will be opened for parking. 
  • Nighttime Security Precautions:  With spring & summer arriving and outdoor patios opening up between 7th and 9th, there is an increase in pedestrian traffic along Pacific Avenue.  The contractor will be taking additional measures to make the work areas along the sidewalks  as safe as possible for the public.

Monday, April 15, 2013

Council Briefing on Hybrid Link Expansion Tomorrow


There has been much discussion on the Tacoma City Council’s preferred expansion of the Sound Transit Tacoma Link. Tomorrow, the Council will hear Sound Transit’s evaluation of a hybrid corridor introduced last month that would incorporate different portions of the original proposed routes from the North End Central, Eastside, and North Downtown Central corridors.
Additionally, Sound Transit will also present information on a different hybrid option.

The Council plans to form a resolution on April 30 in support of a preferred route. For more information, visit the City Council’s website.

Tuesday, April 09, 2013

The Pacific Avenue Streetscape April 9 Weekly Construction Update

Construction Schedule & Progress

• Sidewalks:  The last portions of the sidewalk on the east side of Pacific Avenue between S. 9th & S.13th Street should be poured by the end of this week. 
• Curb & Gutter:  The last portions of the curb & gutter on the east side of Pacific Avenue between S. 9th & S.13th should be poured by the end of this week.
• Bulb Outs: The new bulb out on the SE corner of S. 9th Street is expected to be completed by the end of this week.  Currently this work impacts eastbound and westbound traffic on S. 9th Street.
• Rain Garden: Irrigation and concrete work is ongoing as we progress through each rain garden. The liners will be installed this week with the under drain pipes and drainage gravel placed shortly after. 
• Planters:  The planting of trees & shrubs will begin later this week.
• Vault Infill: Work on the vault infill at 1007 Pacific Avenue began a few weeks ago and is expected to be complete by the end of this month.
• Traffic Control: Traffic control and temporary pedestrian access is in place on the east side of Pacific Avenue between S. 9th and S.13th. The outside lane of northbound through traffic and the parallel parking lane is closed for construction work.
• Daffodil Parade:  The 80th Annual Daffodil Parade will be taking place this Saturday, April 13th.  The parade route will be on Pacific Avenue from S.11th through S.19th Street, with queuing along Pacific Avenue from S. 7th to S.11th, including side streets. 
• Y Run for Kids:  The YMCA will be hosting their annual Y Run for Kids this Saturday with registration beginning at 7 am and the event ending just before the Daffodil Parade.  The run begins and ends in the 1500 block of Pacific Avenue at Tollefson Plaza. 

Road Closures for Daffodil Parade


The flowers are blooming, the birds are chirping, and it is time for the 80th annual Daffodil Parade! The parade will take place this Saturday, April 13 with the following roads closed from 5 a.m to noon:
• A Street, Ninth Street to 24th Street
• Pacific Avenue, from Ninth Street to 24th Street
• Commerce Street, from Ninth Streeth to 24th Street
• East 11th Street from Market Street to Portland Avenue
• East 11th Street will be one-way eastbound from St. Paul to Portland Avenue


Impact on local freeways

The A Street and 15th Street exits from I-705 will be closed.  Schuster Parkway will remain open and Commerce Street will be accessible from the Stadium exit.  The I-705 on-ramp at Ninth Street will be open and drivers will be able to cross Pacific Avenue at SR-509 and 21st Street. 

For more information on road closures associated with the Tacoma Daffodil Parade, please call (253) 591-5932.

Opus Bank to Open Downtown


Downtown Tacoma continues to attract new businesses to the area. Irvine, California- based Opus Bank announced it will be opening a new banking office on the first floor of the Tacoma-Pierce County Chamber of Commerce building at the corner of Pacific and 11th Street. Additional information can be found on the Business Examiner website.

Monday, April 08, 2013

Pacific Avenue Special Meeting Held Thursday


The Pacific Avenue Streetscape reconstruction is well underway. While there have been notable delays the City and the City’s contractor remain committed to completing the project this November.

In order to discuss potential changes to the project’s phasing and sequencing, gain stakeholder input, as well as answer any questions, stakeholders are invited to attend a special meeting held this Thursday, April 11 from 9:30 – 10:30 a.m. at the Tacoma- Pierce County Chamber's offices located at 950 Pacific Avenue, Suite 300 Tacoma, Washington 98401.

For more information visit the project website.

Tuesday, March 05, 2013

See the Murray Morgan Bridge in Action


Work on the Murray Morgan Bridge is wrapping up as the contractor performs final commissioning tests of the bridge operating equipment. During the tests, the bridge will be raised and lowered several times each day. Stop by and witness the rehabilitated bridge in action!

The Murray Morgan Bridge is located at A Street and South 11th in downtown Tacoma. Testing will be performed Monday, March 4 through Thursday, March 7 from 6 PM until 9 PM, Friday, March 8 from 6 PM through 6 AM Saturday, March 9, and finish up Saturday, March 9 from noon to 9 PM.

The bridge will remain open to traffic during testing, however prepare for delays.